Timeline for the 2008 Great Day of Service
| September 17 |
Leadership Committee Meeting |
| September and Ongoing |
GDS Committees organize & begin planning
GDS Website under development
Sponsorships requested
|
| October 1 |
Website on line |
| October 10 |
Letters & Project Request Forms mailed to agencies
Other project ideas developed |
| November 20 |
Project Request Form return deadline
Other project ideas finalized |
| November 26 - January 4 |
Site visits and evaluation of project requests |
| January 11 |
Project selection by Project Chairs and Project Evaluation Team |
| January 7 - 31 |
Projcet descriptions developed for marketing materials and website |
| Week of January 14 |
Agencies and organizations notified of project selections |
| January 14 6:30P |
Leadership Committee Meeting |
| January 26 |
GDS Fundraiser: Dinner and Art Auction
Cotton Patch Gospel Performance |
| February 1 - 15 |
Team Leader recruitment |
| February 10 - March 9 |
Volunteer Sign-up - Online and by paper |
| March 3rd 6:30P |
Team Leader Meeting and Project Assignment |
| March 4 - 7 |
Team Leaders visit agencies to review projects and assess project needs
Team Leaders determine who will purchase project supplies
|
| March 9 |
Volunteer Sign-up ends |
| March 10 and ongoing |
Volunteer placement |
| March 10 |
Leadership Committee Meeting (tentative) |
| March 10 - 17 |
Team Leaders notified of names of Team Members |
| Week of March 17 |
Team Leaders contact Team Members
Project supplies and materials purchased |
| Week of March 24 |
Final preparations and walk-through |
| March 29 |
Great Day of Service !! |
| March 30 |
Celebration Sunday
GDS Evaluations solicited online and by paper |
| By April 30 |
Evaluations tabulated
Wrap-up Meeting |